Tekenpunt / Projects / Warehouse new build Barneveld
Completed project · Warehouse new build PLAN N°PRJ-BNV-2024 / SCALE 1:100 / 2024

New warehouse build in Barneveld

An agricultural entrepreneur in Barneveld needed a robust industrial warehouse of 640 m². We handled the complete design, the structural calculations for the steel portal frames and the building permit. Permit granted, contractor started immediately.

TypeWarehouse new build
LocationBarneveld
Surface area640 m² warehouse
Lead timeBuilding permit 8 weeks
Year2024
ResultSteel portal frame warehouse
§01 From sketch to completion

The complete process

01 · Challenge

Space for machinery and storage on an agricultural site

A contractor in the Barneveld region had been struggling with an overcrowded storage barn for years. The growing machinery, including a large combine harvester and several tractors, no longer fitted in it. There was space on the agricultural site for a new warehouse, but the zoning plan set requirements for maximum eave height, facade cladding and landscape integration. At the same time, the structure had to be calculated for the high snow and wind loads.

02 · Our approach

Steel portal frames, fully calculated

We designed a steel portal frame warehouse with a clear span of 20 metres and an eaves height of 6 metres. The facades were clad with steel profiling in a colour matching the surrounding buildings. The structural calculation for the portal frames, roof structure and foundation slab was entirely handled by us. The building permit was submitted to the municipality of Barneveld. We coordinated the landscape integration in accordance with the applicable rural zoning plan.

03 · Result

640 m² warehouse, permit obtained in 8 weeks

The building permit was granted within 8 weeks of submission. The contractor could start immediately with the construction-ready documents, including foundation, trusses and facade cladding. The warehouse has a clear span without intermediate columns, so that the full 640 m² provides usable floor area for machinery, storage and work activities. After completion, the client was able to store his entire fleet of machines under cover.

Key project details

Drafting
Design + construction drawings
Permit
Building permit in 8 weeks
Structure
Portal frames, foundation, roof structure
Span
20 m clear span (no intermediate columns)
Lead time
Sketch to permit in 8 weeks

What we delivered

  • Site plan, floor plan, elevations and sections
  • Complete building permit application with the municipality of Barneveld
  • Structural calculation for portal frames and foundation slab
  • Wind load and snow load calculation in accordance with NEN-EN 1991
  • Execution details for facade cladding and roof connection
  • Landscape integration drawing in accordance with the zoning plan
§03 Having a warehouse built yourself?

Got a similar project in mind?

Whether you build in Barneveld, the Veluwe or elsewhere in the Netherlands: we handle design, structure and permits from A to Z. Since 2016, 800+ projects. A no-obligation quote within 1 working day.

Last updated: June 2026 Content reviewed by the Tekenpunt team · in-house architect & KIWA-certified structural engineer